| No |
Tanggal |
GI |
Bay/Unit |
Pekerjaan |
Jenis |
Keterangan |
Status |
Info |
Aksi |
| 11 |
03/02/2026 |
GIS GANDARIA |
CIRACAS 2 |
HAR OFF BAY LINE |
ROT |
HAR OFF BAY LINE CIRACAS 2 |
Selesai
|
|
|
| 12 |
03/02/2026 |
GIS CIRACAS |
GANDARIA 2 |
HAR OFF BAY LINE |
ROT |
HAR OFF BAY LINE GANDARIA 2 |
Selesai
|
|
|
| 13 |
03/02/2026 |
GIS ANTASARI |
DURENTIGA 1 |
STANDARISASI SETTING & LOGIC |
ROT |
STANDARISASI SETTING & LOGIC B... |
Selesai
|
1 P |
|
| 14 |
27/01/2026 |
GIS ANTASARI |
TRAFO 2 |
Har Off |
ROT |
laptek: nando, alat: zul |
Selesai
|
|
|
| 15 |
27/01/2026 |
GIS KEMANG |
ANTASARI 1 |
STANDARISASI |
ROT |
BARENG HAR SKTT |
Selesai
|
|
|
| 16 |
27/01/2026 |
GIS ANTASARI |
KEMANG 1 |
STANDARISASI |
ROT |
BARENG SKTT |
Selesai
|
|
|
| 17 |
20/01/2026 |
GIS ANTASARI |
TRAFO 1 |
HAR OFF |
ROT |
|
Selesai
|
|
|
| 18 |
13/01/2026 |
GIS PONDOK INDAH |
TRAFO 3 |
HAR OFF |
ROT |
PIC PIC |
Selesai
|
|
|
| 19 |
12/01/2026 |
GIS PONDOK INDAH |
TRAFO 2 |
har off |
ROT |
|
Selesai
|
|
|