| No |
Tanggal |
GI |
Bay/Unit |
Pekerjaan |
Jenis |
Keterangan |
Status |
Info |
Aksi |
| 1 |
25/02/2026 |
GIS BINTARO BARU |
RECTI UNIT 3 |
EQUALIZING BATERAI UNIT 3 |
NON-ROT |
|
Selesai
|
|
|
| 2 |
25/02/2026 |
GI PETUKANGAN |
RECTI UNIT 2 |
EQUALIZING BATERAI UNIT 2 |
NON-ROT |
|
Selesai
|
|
|
| 3 |
24/02/2026 |
GIS BINTARO BARU |
RECTI UNIT 2 |
EQUALIZING BATERAI UNIT 2 |
NON-ROT |
|
Selesai
|
|
|
| 4 |
24/02/2026 |
GI PETUKANGAN |
RECTI UNIT 1 |
EQUALIZING BATERAI UNIT 1 |
NON-ROT |
|
Selesai
|
|
|
| 5 |
23/02/2026 |
GIS BINTARO BARU |
REMOTE READING |
PENARIKAN KABEL LAN DAN KONFIGURASI REMOTE READING INCOMING T1, T2, T3 |
NON-ROT |
SAMPAI TANGGAL 24 |
Selesai
|
|
|
| 6 |
23/02/2026 |
GIS BINTARO BARU |
RECTI UNIT 1 |
EQUALIZING BATERAI UNIT 1 |
NON-ROT |
|
Selesai
|
|
|
| 7 |
21/02/2026 |
GIS CIRENDEU |
TRAFO 2 |
HAR OFF TRAFO 2 GIS CIRENDEU |
ROT |
SEKALIAN PERBAIKAN PD DAN HAR ... |
Selesai
|
2 P |
|
| 8 |
14/02/2026 |
GIS BINTARO |
TRAFO 1 |
Penggantian AVR |
NON-ROT |
Berbarengan pemasangan sensor |
Selesai
|
1 P |
|
| 9 |
09/02/2026 |
GIS BINTARO BARU |
BINTARO 2 |
HAR OFF BAY LINE |
ROT |
HAR OFF BAY LINE BINTARO 2 |
Selesai
|
|
|
| 10 |
09/02/2026 |
GIS BINTARO |
BINTARO BARU 2 |
HAR OFF BAY LINE |
ROT |
HAR OFF BAY LINE BINTARO BARU ... |
Selesai
|
|
|